Grambling State University is committed to creating innovative learning, leisure, and athletic environments that foster scholarship, enrichment, and a strong sense of community for our students, faculty, staff, and supporters. We are dedicated to continuous growth and development, reflecting our mission to advance academic excellence and community engagement. Follow the links below to stay updated on our progress and join us in building a brighter future for Grambling State University.
Projects as of March 15, 2026
| Project Name | Primary Use | Funding Source | Status |
|---|---|---|---|
| Assembly Center Foundation and Underground Piping Repairs | Infrastructure | State of Louisiana - Capital Outlay | Completed | Fall 2024 |
| Central Avenue Improvements | Infrastructure | State of Louisiana - Appropriations | Completed | Fall 2024 |
| Digital Library and Learning Commons | Research/Study | State of Louisiana - Capital Outlay | Completed | Fall 2024 |
| Grambling Hall Registrar File System | Technology | Title III | Completed | Fall 2024 |
| JTS Computer Lab Renovations | Academic | Title III | Completed | Fall 2024 |
| JTS Stairwell Treads | Asset Upgrades | Title III | Completed | Fall 2024 |
| Painting of Carver Hall Exterior | Asset Upgrades | Title III | Completed | Fall 2024 |
| Track Resurfacing | Athletic/Intramural | Student Athletic Fee | Completed | Fall 2024 |
| Aquaculture Center Demolition | Infrastructure | State of Louisiana - Capital Outlay | Completed | Spring 2025 |
| Campus Utility Infrastructure Assessment | Infrastructure | State of Louisiana - Capital Outlay | Completed | Spring 2025 |
| Carver Hall Room 107 | Renovation | Title III | Completed | Spring 2025 |
| Carver Hall Room 174 | Renovation | Title III | Completed | Spring 2025 |
| Carver Hall Room 182 | Renovation | Title III | Completed | Spring 2025 |
| Carver Room 185 | Renovation | Title III | Completed | Spring 2025 |
| Foster-Johnson Health Center | Student Support | Grant/GSU | Completed | Spring 2025 |
| GSU TV Center | Renovation | Title III | Completed | Spring 2025 |
| HVAC Infrastructure Upgrades (Boilers, Chillers, Pumps, & Controls) | Infrastructure | HEERF | Completed | Spring 2025 |
| Intramural Center Skylight Replacement | Infrastructure | State of Louisiana - Capital Outlay | Completed | Spring 2025 |
| Jeanes Hall Building Abatement and Demolition | Infrastructure | State of Louisiana - Capital Outlay | Completed | Spring 2025 |
| Laundry Building Abatement and Demolition | Infrastructure | State of Louisiana - Capital Outlay | Completed | Spring 2025 |
| Old Property Warehouse Demolition | Infrastructure | State of Louisiana - Capital Outlay | Completed | Spring 2025 |
| Old Gazebo Demolition | Infrastructure | State of Louisiana - Capital Outlay | Completed | Spring 2025 |
| President's Garage, Building Abatement, and Demolition | Infrastructure | State of Louisiana - Capital Outlay | Completed | Spring 2025 |
| Baseball Wall Padding | Athletics | Student Athletic Fee | Completed | Summer 2025 |
| Brown Hall Room 215 Renovation | Academic | Title III | Completed | Summer 2025 |
| Brown Hall Room 239 Renovation | Academic | Title III | Completed | Summer 2025 |
| Soccer Field Observation Deck | Athletics | Grant | Completed | Summer 2025 |
| Carver Room 167 Renovations (Biology) | Academic | Title III | Completed | Fall 2025 |
| Charles P. Adams Room 207 | Renovation | Title III | Completed | Fall 2025 |
| Eddie G. Robinson Memorial Stadium Wall Padding | Athletics | Grant | Completed | Fall 2025 |
| Electrical Resiliency and Improvement | Infrastructure | State of LA - Capital Outlay | Completed | Fall 2025 |
| Soccer Field Fence Project | Athletics | Student Athletic Fee | Completed | Fall 2025 |
| Stadium Support Roof Repairs | Athletics | Building Use Fee | Completed | Fall 2025 |
| T.L. James Room 104 Renovation | Academic | Title III | Completed | Fall 2025 |
| T.L. James Room 132 Renovation | Academic | Title III | Completed | Fall 2025 |
| Charles P. Adams Room 321 | Renovation | Title III | Completed | Spring 2026 |
| JTS Room 120 | Renovation | Title III | Completed | Spring 2026 |
| JTS Room 219 | Renovation | Title III | Completed | Spring 2026 |
| JTS Room 234 | Renovation | Title III | Completed | Spring 2026 |
| JTS Room 333 | Renovation | Title III | Completed | Spring 2026 |
| Woodson Hall Renovation 231/232 (Writing Lab) | Academic | Title III | Completed | Spring 2026 |
| Electrical Resiliency and Improvement | Infrastructure | State of Louisiana - Capital Outlay | Construction (In-Progress) |
| Property and Receiving Warehouse | Operations | Insurance | Construction (In Progress) |
| Soccer Field Fence Project | Athletics | State of Louisiana - Appropriations | Construction (In Progress) |
| Stadium Support Locker Rooms & Floors | Athletics | Building Use Fee/State of Louisiana - Appropriations | Construction (In Progress) |
| Stadium Support Roof Repairs | Athletics | Building Use Fee | Construction (In Progress) |
| Student Success Center | Student Support | HEERF through Black and Gold Facilities, Inc. | Construction (In Progress) |
| T.L. James Engineering Lab Renovation | Academic | Title III | Construction (In Progress) |
| T.L. James Room 82 Renovation | Academic | Title III | Construction (In Progress) |
| T.L. James Room 104 Renovation | Academic | Title III | Construction (In Progress) |
| Warehouse Fire Rebuild | Administrative | Insurance | Construction (In-Progress) |
| Black and Gold Room | Academic | Grant | Pre-Construction |
| Carver Hall Roof | Academic | State of Louisiana - Deferred Maintenance | Pre-Construction |
| Carver Hall Room 167 | Renovation | Title III | Pre-Construction |
| Charles P. Adams Room 200 | Academic | Title III | Pre-Construction |
| Charles P. Adams Room 212 | Academic | Title III | Pre-Construction |
| Charles P. Adams Room 303 | Renovation | Title III | Pre-Construction |
| Charles P. Adams Room 316 | Academic | Title III | Pre-Construction |
| Charles P. Adams Room 322 | Academic | Title III | Pre-Construction |
| Charles P. Adams Room 331 | Academic | Title III | Pre-Construction |
| College Ave Overlay | Infrastructure | State of Louisiana - Appropriations | Pre-Construction |
| Criminal Justice Building | Academic | State of Louisiana - Capital Outlay | Pre-Construction |
| Eddie G. Robinson Museum Foundation | Infrastructure | State of Louisiana - Appropriations | Pre-Construction |
| Eddie G. Robinson Museum Roof | Administrative | State of Louisiana - Capital Outlay | Pre-Construction |
| Elevator Modernization I | Administrative | State of Louisiana - Deferred Maintenance | Pre-Construction |
| Hobdy Assembly Center Arena Lighting Upgrades | Athletics | Grant | Pre-Construction |
| Holland Hall Laundry Room Restoration | Residential | Title III | Pre-Construction |
| Indoor Practice Facility | Athletics | State of Louisiana - Appropriations | Pre-Construction |
| Intramural Indoor Track Floors and Wall Padding | Administrative | University | Pre-Construction |
| Men's Gym Roof | Athletics | State of Louisiana - Deferred Maintenance | Pre-Construction |
| Men's Gym Roof Repair | Athletic | Student Athletic Fee | Pre-Construction |
| Residence Hall | Campus Living and Housing | University and HEERF through Black and Gold Facilities, Inc. | Pre-Construction |
| School of Nursing Roof | Administrative | State of Louisiana - Capital Outlay | Pre-Construction |
| Sidewalk, Sinkhole, and Concrete Repairs | Infrastructure | State of LA - Deferred Maintenance | Pre-Construction |
| School of Nursing Simulation Lab Renovation | Academic | Title III | Pre-Construction |
| Storm Drainage Repair | Infrastructure | FEMA and FP&C | Pre-Construction |
| Tiger Park | Athletic | Student Athletic Fee | Pre-Construction |
| T.L. James Engineering Lab Renovation | Academic | Title III | Pre-Construction |
| T.L. James Room 73 Renovation | Academic | Title III | Pre-Construction |
| T.L. James Room 82 Renovation | Academic | Title III | Pre-Construction |
| T.L. James Room 87 Renovation | Academic | Title III | Pre-Construction |
| T.L. James Room 104 Renovation | Academic | Title III | Pre-Construction |
| T.L. James Room 132 Renovation | Academic | Title III | Pre-Construction |